New Peschiera Acquedot
read moreThe intervention focuses on the construction of a new water tank in reinforced concrete with a capacity of 2,000 m³, located in the Belvedere area, Municipality of Fiano Romano. The project also includes the related connection and discharge pipes.
Civil works
Tank
Construction of a reinforced concrete tank with all the necessary structures.
Installation of electromechanical, electrical and video surveillance systems.
External Arrangements
Construction of an access ramp, fences and green spaces around the tank.
Discharge siphon
Construction of a DN400 cast iron pipe for the outflow of water into the ditch and bank protection works.
Network-related works
Power supply pipes:
Construction of a DN400 cast iron supply pipe, including the line structures, from the manoeuvring chamber.
Construction of a DN300 cast iron supply pipe with the related line structures.
Supply pipelines:
Construction of a DN300 cast iron supply pipe, up to the joint outside the manoeuvring chamber.
Connection of the new pipelines to the existing network and testing of the networks.
The project solves several critical issues that emerged from the studies conducted by Acea Infrastructure, including the considerable variations in network altitude, a high degree of leakage and the insufficient compensation capacity of existing tanks.
The tank is supplied by the Capodimonte tank via a DN300 cast iron pipe (L= 2,157 m). The pipeline initially follows the provincial road 19/a – Via Civitellese for about 500 m, then continues for about 900 m along the West beltway "S.P. Tiberina – S.P. Civitellese".
The connection to the distribution network takes place through a DN400 cast iron pipe (L= 603 m). In addition, a new DN300 cast iron pipe (L= 1,133 m) was built to feed the areas to the northeast of the historic centre and around Via Tiberina.
A DN400 duct (L= 310 m) was made of spheroidal cast iron for the delivery of overflow and emptying water to the Fosso dei Ponticelli.
The tank consists of two rectangular basins with internal dimensions of 12.90 x 21.00 m each. The manoeuvring chamber has dimensions of 4.50 x 30.80 m.
Customer | Acea Ato 2 |
---|---|
Site | Municipality of Fiano Romano |
Timetable | Start: September 2024 |
Detail of the service |
|
Service execution quota
100% Acea Infrastructure SpA
Number of tanks
2
Amount of works
10.341.580 €
(of which €427,720 are for security costs)
Total capacity
2.000 m3
Residents in the district served by the project
7590 - with the expected demographic increase (time horizon 30-40 years), we will reach 15,280 inhabitants (project value).
Quotas
maximum water head 131.00 m above sea level and bottom at 127.00 m above sea level (maximum water head equal to 4 m)
Pipelines
approx. 3,9 Km