New Peschiera Acquedot
read moreThe project involves the construction of a new biofiltration macro-module in the Roma Sud Purification Plant. This new system is located between the existing second biofiltration line (modules 3 and 4) and the second primary sedimentation section.
Structure of the macro-module
Composed of two parallel modules.
Each module is divided into multiple unit filtration cells.
Processing capacity
The two new modules can handle a total flow rate of approximately 2 m³/s.
With the creation of the two new modules, it is possible to carry out a secondary treatment on the entire incoming flow and complete all the interventions on the sewage line provided for in the general plant adaptation plan. In addition, the new system guarantees a significant increase in the overall purification efficiency, and provides an adequate safety margin compared to possible out-of-service treatment units, ensuring continuity of service.
Customer | Acea Ato 2 |
---|---|
Site | Municipality of Rome |
Timetable | Start: May 2024 |
Detail of the service |
|
Service execution quota
100% Acea Infrastructure SpA
Work amount
40.000.000 €
(of which 1.497.300 € are for security costs)
Maximum potential of the new sector
2,34 m3/s
Number of modules:
2
Number of filters per module
8
Filter unit area
approx. 100 m2
Module Size
Length BIOFOR C+N 12.68 m, Width BIOFOR C+N 7.95 m, Height 6.09 m
Biofilter technology
up flow