The project involves the construction of a new biofiltration macro-module in the Roma Sud Purification Plant. This new system is located between the existing second biofiltration line (modules 3 and 4) and the second primary sedimentation section.

 

Project specifications

Structure of the macro-module

 

  • Composed of two parallel modules.

  • Each module is divided into multiple unit filtration cells.

     

Processing capacity

 

  • The two new modules can handle a total flow rate of approximately 2 m³/s.

 

With the creation of the two new modules, it is possible to carry out a secondary treatment on the entire incoming flow and complete all the interventions on the sewage line provided for in the general plant adaptation plan. In addition, the new system guarantees a significant increase in the overall purification efficiency, and provides an adequate safety margin compared to possible out-of-service treatment units, ensuring continuity of service.

Project details

 

Customer

Acea Ato 2

Site

Municipality of Rome

Timetable

Start: May 2024
End: November 2026

Detail of the service

  • Engineering services during the execution of works (Works Management).

 
  • Procurement of services and supplies, and the coordination of all the work necessary to provide the Customer with the finished work in a state-of-the-art manner.

Key numbers

Service execution quota

 

100% Acea Infrastructure SpA

Work amount

 

40.000.000 €

(of which 1.497.300 € are for security costs)

Maximum potential of the new sector

 

2,34 m3/s

Number of modules:

 

2

Number of filters per module

 

8

Filter unit area

 

approx. 100 m2

Module Size

 

Length BIOFOR C+N 12.68 m, Width BIOFOR C+N 7.95 m, Height 6.09 m

Biofilter technology

 

up flow

Discover all the projects

zoom su una mano che tiene in mano una provetta di laboratorio vicino a dei macchinari

PROMISCES Project

read more
Pila di caschi da operaio

Safety inspections on grids and service maintenance framework agreements

read more
porzione della struttura in ferro dell'infrastruttura

IV linea San Vittore

read more
Una uomo in un laboratorio riempie delle provette

Bioref-Full Project

read more
Laptop poggiato su una scrivania d'ufficio. Si vede anche uno smartphone e una pianta di cactus

The Co.Si. platform in support of the verification of professional technical suitability

read more
Operaio che lavora su una infrastruttura idrica in cui si vede anche una vasca d'acqua

Construction of the Belvedere water tank

read more
contenitori di plastica

Determination of microplastics in water for human consumption

read more
Due uomini e una donna in tenuta ad alta visibilità pianificano delle attività in un magazzino

Safety coordination during the execution stage in 2023-2024

read more
infrasturttura idrica con una vasca piena d'acqua, delle strutture in ferro e gli alberi sullo sfondo

Revamping Depuratore Santa Marinella Nord

read more
mani che pesano una sostanza su una bilancia in un contesto di laboratorio

Enhancement of purification plant grids

read more
vasca di raccolta dell'acqua nell'infrastruttura dell'acquedotto del peschiera

Coordination of safety during the design phase in the New Peschiera Aqueduct

read more
operaio al lavoro su un macchinario. ha alle spalle un grande tubo arancione

Doubling of the VIII siphon - Casa Valeria / exit Galleria Ripoli section

read more
giovane ragazza in fase di analisi in un laboratorio

Micro-pollutants in the human body

read more
Vista dall'alto del paesaggio di Colle Sant'Angelo, con alberi e bacino idrico

Monte Castellone - Colle Sant'Angelo duct

read more