New Peschiera Aqueduct
read more
This project focused on the construction of a new sector for the upgrading of biogas in the Roma Nord purification plant, located downstream of a new dedicated pre-treatment section. The plant has been designed to improve energy efficiency, reduce environmental impact, and optimise service charges, continuously generating around 1,400,000 Sm³ per year of biomethane.
Project details
Biogas upgrading line with nominal capacity of 260 Nm³/h.
Control and measurement cabinet (REMI cabinet) for controlling the quality and quantity of biomethane fed to the network.
Post-combustion section of the off-gas exiting the upgrading membranes.
Customer | Acea Ato 2 |
---|---|
Site | Municipality of Rome |
Timetable | Start: February 2023 |
Detail of the service | Engeneering services during the execution of works (Works Management)
|
Acea Ato 2
Municipality of Rome
Start: February 2023
End: Dicember 2023
Engeneering services during the execution of works (Works Management)
Procurement of services and supplies, and the coordination of all the work necessary to provide the Customer with the finished work in a state-of-the-art manner.
Service execution quota: 100% Acea Infrastructure SpA
Amount of works: 5.885.500 € (di cui 118.300 € costi della sicurezza)
Nominal flow rate of wet biogas entering the line
Average volume content of CH4 in wet biogas: 65 %
Average volume content of CO2 in wet biogas: 30 %
Average volume content of CH4 in biomethane: > 97 %
Guaranteed purification efficiency > 99,3 %
Average volume content of CH4 in the off-gas: < 2 %
Hours of plant operation per year (expected value): > 8000 h/anno
Hours of plant operation on a daily basis: 24 h/giorno
Max expected biomethane potential on an annual basis: 1.400.000 Sm3/anno