Roma Sud energy optimisation

impianto idrico con delle cisterne d'acqua e un prato verde

Description and objectives

 

As part of the energy re-efficiency plan of the Roma Sud sewage purification plant, a replacement of the surface mechanical ventilation system of the activated sludge section has been planned. The previous system, consisting of brushed rotors, has been replaced with a new system of fine bubble bottom diffusers powered by high-efficiency compressors.

Project specifications

    Creation of a new ventilation system consisting of fine bubble bottom diffusers powered by high-efficiency compressors.

    Process efficiency increase:

     

    • Guarantee of the air supply necessary for the oxidation and nitrification process.

       

    • Capacity to treat the section with a flow rate of 4.5 m3/s.

    Reduction of energy consumption:

     

    • Consistent reduction in energy consumption related to the ventilation of the section thanks to the new system configuration.

    Project details

     

    Customer

    Acea Ato 2

    Site

    Municipality of Rome

    Timetable

    Start: December 2021
    End: August 2025

    Detail of the service

    • Engineering services during the execution of works (Works Management).

       

    • Procurement of services and supplies, and the coordination of all the work necessary to provide the Customer with the finished work in a state-of-the-art manner.

    Key numbers

    • Service execution quot: 100% Acea Infrastructure SpA

       

    • Work amount: 9.241.300 € (of which €380,000 are for security costs)

       

    • Oxidation tanks: 3 (Carrousel type activated sludge)

       

    • Flow rate treated: 4.5 m3/s

       

    • Total volume of tanks: about 52,500 m3 (usable depth 3.5 m)

       

    • No. of diffusers: 2,100 fine bubble diffusers (with 20’’ EPDM membrane)

       

    • No. of flow generators: 8 flow generators per tank (each consisting of a 3-bladed propeller)

       

    • No. of compressors in the air production station: 6+1R high-efficiency centrifugal compressors

       

    • Energy savings compared to the current structure: 50% 

    Discover all the projects

    zoom su una mano che tiene in mano una provetta di laboratorio vicino a dei macchinari

    PROMISCES Project

    read more
    Pila di caschi da operaio

    Safety inspections on grids and service maintenance framework agreements

    read more
    porzione della struttura in ferro dell'infrastruttura

    IV linea San Vittore

    read more
    Una uomo in un laboratorio riempie delle provette

    Bioref-Full Project

    read more
    Laptop poggiato su una scrivania d'ufficio. Si vede anche uno smartphone e una pianta di cactus

    The Co.Si. platform in support of the verification of professional technical suitability

    read more
    contenitori di plastica

    Determination of microplastics in water for human consumption

    read more
    Due uomini e una donna in tenuta ad alta visibilità pianificano delle attività in un magazzino

    Safety coordination during the execution stage in 2023-2024

    read more
    mani che pesano una sostanza su una bilancia in un contesto di laboratorio

    Enhancement of purification plant grids

    read more
    vasca di raccolta dell'acqua nell'infrastruttura dell'acquedotto del peschiera

    Coordination of safety during the design phase in the New Peschiera Aqueduct

    read more
    operaio al lavoro su un macchinario. ha alle spalle un grande tubo arancione

    Doubling of the VIII siphon - Casa Valeria / exit Galleria Ripoli section

    read more
    giovane ragazza in fase di analisi in un laboratorio

    Micro-pollutants in the human body

    read more
    Vista dall'alto del paesaggio di Colle Sant'Angelo, con alberi e bacino idrico

    Monte Castellone - Colle Sant'Angelo duct

    read more